Delmia Tutorial-Creating the Process Plan

Procedure:

In this exercise, a process plan will be created for the RH Body Side Assembly.  The standard commands in the Activities toolbar will be used.
Using the Resource Centric approach in the next step, the tasks will be assigned to activities. 
Physical activities are imported into the process from a user activity library.  Dress-up activities such as viewpoint, visibility, and text message activities are created under the process node.

Open to the DPM Fastener Process Planner workbench.  From the main menu, select Start / Digital Process for Manufacturing / DPM Fastening Process Planner

4.  The Create Activity dialog box appears.  Click on the More >> button to see the Station Activity Attributes.  Change the Name to Station 1 and click on OK.  Create another activity and name it, Station 2.

When you insert a station activity in the PPR tree, it will always be a successor to another station activity or a child of the main process.  Stations activities children are other activities; it cannot be a child of, say a clamping activity.  